隧道爆破振动对新浇超短龄期混凝土二衬的影响
贺泳超1,陈秋南1, 2,衣利伟1,黄向韬1,曾奥1,周相识3,周光裕3

(1. 湖南科技大学 土木工程学院,湖南 湘潭,411201;
2. 湖南科技大学 岩土工程稳定控制与健康监测湖南省重点实验室,湖南 湘潭,411201;
3. 湖南尚上建设开发有限公司,湖南 长沙,410022
)

摘 要: 为探究隧道施工爆破振动对隧道二衬新浇筑混凝土的影响,以Ⅳ级围岩台阶法施工的上台阶掌子面爆破作为震源,对不同新浇超短龄期的4个等级强度的混凝土试块分别在不同爆心距下进行爆破振动试验。待所有试块养护28 d后,采用非金属超声检测仪分别测试超声波在受振混凝土试块和普通混凝土试块中的传播速度,通过对两者传播速度进行对比分析,判断爆破受振混凝土试块的缺陷与损伤程度。研究结果表明:在Ⅳ级围岩上台阶施工情况下,爆心距为15 m处的混凝土试块受爆破振动的影响最大,在30 m处的混凝土试块具有最强抵抗爆破振动的能力,30 m之后爆破振动对混凝土试块的损伤较小且逐渐趋于稳定。这可为缩短二衬至掌子面距离、确保隧道施工安全提供参考。

 

关键字: 爆破振动;超短龄期混凝土;超声波检测;混凝土缺陷

Influence of tunnel blasting vibration on secondary lining of new ultra short age concrete
HE Yongchao1, CHEN Qiunan1, 2, YI Liwei1, HUANG Xiangtao1,ZENG Ao1, ZHOU Xiangshi3, ZHOU Guangyu3

1. School of Civil Engineering, Hunan University of Science and Technology, Xiangtan 411201, China;
2. Hunan Provincial Key Laboratory of Geotechnical Engineering for Stabilility Control and Health Monitoring, Hunan University of Science and Technology, Xiangtan 411201, China;
3. Hunan Communication & Water Conservancy Group Ltd, Changsha 410022, China

Abstract:In order to explore the influence of blasting vibration in tunnel construction on newly poured concrete of the second lining of tunnel, taking the blasting of upper bench face of stage IV surrounding rock bench construction as the source of vibration,blasting vibration tests were carried out on four kinds of concrete blocks with different strengths of different newly poured ultra-short ages at different spacings of blasting centers. After 28 d of curing, non-metallic ultrasonic testing instrument was used to test the propagation speed of ultrasonic wave in vibration concrete and ordinary concrete. Through the comparative analysis of the propagation speed, the defect and damage degree of the blasting vibration concrete were judged. The results show that under the condition of step construction in grade IV surrounding rock, the concrete blocks with a distance of 15 m from the blasting core are most affected by blasting vibration, and the concrete blocks with a distance of 30 m have the strongest ability to resist blasting vibration. Beyhond 30 m, the damage of blasting vibration to the concrete blocks is less and tends to be stable. The conclusion provides a reference for shortening the distance between the second lining and the face of tunnel to ensure the safety of tunnel construction.

 

Key words: blasting vibration; ultra short age concrete; ultrasonic test; concrete defects

中南大学学报(自然科学版)
  ISSN 1672-7207
CN 43-1426/N
ZDXZAC
中南大学学报(英文版)
  ISSN 2095-2899
CN 43-1516/TB
JCSTFT
版权所有:《中南大学学报(自然科学版、英文版)》编辑部
地 址:湖南省长沙市中南大学 邮编: 410083
电 话: 0731-88879765(中) 88836963(英) 传真: 0731-88877727
电子邮箱:zngdxb@csu.edu.cn 湘ICP备09001153号